S.No Project Duration In Years Cost in crores 
1 Improvement to vizag-Jeypore road from km 173/0 to 198/0 in state of odisha through an EPC Basis contract. 1.6 Year 42
2 Widening and strengthening of Ramanaguda-Bisam Cuttack road (SH-46)---2 Reaches of 19 km in Ramanguda,Rayagada dist. 1 Year 33.5
3 Kalimela to motu(SH 25) - 52km , Orissa - PWD (LWE scheme). 2.5 Years 88
4 Widening and strengthening of Komtalpeta-Muniguda- Tumudibandha road(SH-5)--- 2 Reaches of 16.6 km in Muniguda,Rayagada Dist. 1.3 Year 33.6
5 Malkangiri to balimela(omr road) - 29.2km, Orissa - PWD (LWE scheme). 2 Years 33
6 Balimela to Chithrakonda(State highway SH47)-33km, Orissa - PWD (LWE scheme). 2 Years 45
7 Kalimela to podia(ODR road)- 28km, Orissa - PWD (LWE scheme). 2 Years 35
8 Improvement of Ramanaguda-katiki road (ODR) from 0/00 to 10/800 Km in the district of Rayagada under NABARD. 1 Year 22
9 Widening and strengthening of Koraput-Laxm ipur- Rayagada-Gunpur road (SH- 4)---10.9 km in Gunpur,Rayagada Dist. 1.2 Year 15
10 Construction of Quators for Revenue Department , Construction of academic building for new goverment polytechnic and Construction of Workshop, Hostels, Quarter for new Govt. Polytechnic at Malkangiri. 1.6 Year 16