| S.No | Project | Duration In Years | Cost in crores |
| 1 | Improvement to vizag-Jeypore road from km 173/0 to 198/0 in state of odisha through an EPC Basis contract. | 1.6 Year | 42 |
| 2 | Widening and strengthening of Ramanaguda-Bisam Cuttack road (SH-46)---2 Reaches of 19 km in Ramanguda,Rayagada dist. | 1 Year | 33.5 |
| 3 | Kalimela to motu(SH 25) - 52km , Orissa - PWD (LWE scheme). | 2.5 Years | 88 |
| 4 | Widening and strengthening of Komtalpeta-Muniguda- Tumudibandha road(SH-5)--- 2 Reaches of 16.6 km in Muniguda,Rayagada Dist. | 1.3 Year | 33.6 |
| 5 | Malkangiri to balimela(omr road) - 29.2km, Orissa - PWD (LWE scheme). | 2 Years | 33 |
| 6 | Balimela to Chithrakonda(State highway SH47)-33km, Orissa - PWD (LWE scheme). | 2 Years | 45 |
| 7 | Kalimela to podia(ODR road)- 28km, Orissa - PWD (LWE scheme). | 2 Years | 35 |
| 8 | Improvement of Ramanaguda-katiki road (ODR) from 0/00 to 10/800 Km in the district of Rayagada under NABARD. | 1 Year | 22 |
| 9 | Widening and strengthening of Koraput-Laxm ipur- Rayagada-Gunpur road (SH- 4)---10.9 km in Gunpur,Rayagada Dist. | 1.2 Year | 15 |
| 10 | Construction of Quators for Revenue Department , Construction of academic building for new goverment polytechnic and Construction of Workshop, Hostels, Quarter for new Govt. Polytechnic at Malkangiri. | 1.6 Year | 16 |